Posted on: November 14, 2022

[ARCHIVED] Construction Update 11/10/22: 2022 Annual Street Rehab Project

Notice of Street Paving

Construction Update: 2022 Annual Street Rehab Project

UPDATE 11/10/22: Paving and Slurry Seal is delayed due to cold/wet weather. Paving work will resume on Saturday, November 19, 2022 on 41st, 47th and Doyle Streets. Remaining paving areas on Adeline Street intersections will be completed the week of November 28, 2022. Concrete work will continue through December 9, 2022. 

Project information with schedules/updates can be found at:
https://www.ci.emeryville.ca.us/1215/Annual-Street-Rehab