Quiet Zone Construction Update (August 2023)
- Night Work is coming to Quiet Zone Project Areas as approved by the Emeryville City Council on June 20th.
- Paving operations are planned for the 65th/Shellmound intersection from 5pm-7pm on Friday, August 4th.
- After 7pm, paving operations will continue north on Shellmound Street to 67th Street and the 67th/Hollis Street intersection.
The City expects to be complete with the overall QZ Project in September/October 2023. Establishment of the “Quiet Zone” is expected to occur in early 2024.
For more Project Information and Details, please visit: https://bit.ly/EmeryvilleQZ.